Submittal software for steel contractors and fabricators, built from your Division 05 spec
Submittal software for steel contractors should read Division 05, list every item each section demands with its paragraph reference, and track each package through the GC, the architect and the engineer of record until the stamp comes back. Submittal does that. Upload the project manual and get one register row per required item (erection drawings, shop drawings, delegated connection calculations, mill test reports, welding procedures, welder qualifications, joist and deck layouts, stair and railing designs), so the shop never waits on an approval nobody sent. Plans start at 24 USD a month per active project billed yearly, and the GC and design team you invite are unlimited.

What a steel submittal register has to cover
Steel is fabricated before it reaches site, so the submittal gates the shop, not the field. Material is ordered and cut from approved drawings, delegated connections need a stamped calculation before the detailer can finish, and joists, deck and stairs often come from separate suppliers on separate review cycles. A generic log tells you a package exists. A spec built register tells you which items in each section are still unsent.
| Division 05 section | Typical submittals the spec asks for | Why they hold up the job |
|---|---|---|
| 05 12 00 structural steel framing | Erection drawings, shop drawings, delegated connection calculations stamped by an engineer, mill test reports, bolt and anchor rod certificates, coating data | The shop cannot cut or drill until the drawings come back, and a revised connection restarts detailing |
| 05 12 00 quality requirements | Fabricator and erector certification, welding procedure specifications, welder qualification records | Many specs require proof of certification before shop drawings are even reviewed |
| 05 21 00 steel joist framing | Joist placement drawings, bridging and bearing details, design calculations from the joist supplier | Joists are manufactured to order and lead times run weeks after approval |
| 05 31 00 steel decking | Deck layout drawings, product data, fastening and shear stud details, fire rating listings | Deck layout ties into the joist and beam drawings and the fire rated assemblies |
| 05 40 00 cold formed metal framing | Delegated design calculations, shop drawings, product data | Exterior wall framing designs often need a separate stamped submittal |
| 05 50 00 metal fabrications | Shop drawings for lintels, embeds, ladders, bollards and supports | Embeds are set in concrete long before the steel arrives |
| 05 51 00 and 05 52 00 stairs and railings | Delegated stair and railing design with stamped calculations, shop drawings, finish samples | Stairs are on the critical path for access and egress during construction |
| 01 45 00 testing and special inspections | Inspection reports, bolt tension and weld test results, closeout certifications | Acceptance and final payment wait on the inspection record |
Try it on your own Division 05 sections before you buy. The homepage tool builds the rows for a spec section you upload, so you can see whether it finds the items your project manager would find.
The submittal problems that hold the shop
Most fabrication delays are visible in the submittal log weeks before the shop runs out of approved work.
- Connection calculations that the spec delegates to the fabricator's engineer, submitted after the shop drawings instead of with them
- Erection drawings approved but individual piece drawings returned with comments, then held as a set while the shop sits idle
- Certification and welding records that the spec wants first, forgotten until the architect returns the whole package unreviewed
- Joist and deck packages from separate suppliers that reference beam drawings still in review
- Embeds and misc metals that the concrete trade sets, submitted by someone else and never checked against the steel drawings
- Mill certificates, inspection reports and coating warranties left for closeout, when the GC holds retainage until they arrive
A register built from the spec makes each of these a row with a due date and an owner on day one. Our guide to construction submittal examples shows how a package is numbered and what comes back with it. When a piece drawing returns marked up, what revise and resubmit means explains how to turn comments into a clean second round, and shop drawings versus product data shows which type each Division 05 item is.
From the Division 05 spec to a tracked register
- 1Upload the project manual. Submittal finds the MasterFormat sections, scanned PDFs included, and you select Division 05 plus the administrative, testing and inspection sections that touch steel.
- 2Review the register. Each required item is one row with its paragraph. Action, informational and closeout items are separated, so certifications and mill reports sit next to the shop drawings they support.
- 3Set dates from the schedule. Work each due date back from the erection start, the mill and joist lead times and the detailing time your detailer quotes.
- 4Send and track packages. Each package goes to the GC, the architect and the engineer of record in order, with one of five standard stamps. You see whose turn it is and when it is overdue.
- 5Close out. Inspection reports, bolt and weld test results and coating warranties stay on the list from day one, so retainage is not held for paperwork.
The longer walkthrough is on the construction specification software page.
Steel fabricators, erectors and misc metals shops
- Project managers at structural steel fabricators who run several jobs for different GCs at once
- Erectors who need approved erection drawings and inspection records in one place
- Misc metals, stair and railing fabricators who carry delegated designs through review
- Detailing coordinators who track which drawings are back, approved or held
- Owners of small and mid size steel firms who want one register per job without a seat for every office user
Steel is a subcontract trade on most commercial jobs, so you usually submit into the GC's system and also need your own list. Submittal gives you that list per project, and the GC you invite joins at no cost. Embeds, anchor rods and slab edge angles cross into concrete work, so the concrete contractors page shows the Division 03 side of the same coordination, and the submittal software for subcontractors page covers the sub view across trades. If you are weighing platforms, the best submittal software for subcontractors roundup compares them honestly.
What steel submittal software costs per project
Per user tools charge for every PM, detailer and coordinator who opens a package. Submittal charges for active projects, and the GC, architect and engineers you invite are unlimited.
| Your workload | Submittal plan | Yearly cost billed yearly |
|---|---|---|
| 1 active project | Starter | 288 USD |
| Up to 5 active projects | Team | 888 USD |
| Up to 25 active projects | Business | 2,988 USD |
Monthly billing is 49, 149 and 499 USD. Compare that with the hours spent building a Division 05 register by hand for each award, then with one week of shop time lost while a connection package sits unsent. For vendor by vendor numbers see the submittal software pricing comparison, and for our own limits see the submittal management software page.
Check the submittal against the right reference
Steel specs cite outside standards, and the submittal has to show the work meets them. Structural steel fabrication, erection and the responsibilities for delegated connection design are commonly tied to the AISC Specification and Code of Standard Practice published at aisc.org, and welding procedures and welder qualification are usually referenced to the American Welding Society structural welding code at aws.org. Submittal does not replace engineering review. It makes sure each item is on the list, has an owner and a date, and is not forgotten until the shop or the inspector asks for it.
What to look for in submittal software for steel work
Ask five things before you buy. Does it read the specification itself, or do you type every row? Does each row keep its paragraph reference, so a reviewer can see why it exists? Can you group items into numbered packages, such as one erection package and one connection package per sequence? Does it handle resubmittals as new revisions without losing the history? And does the price follow the number of jobs, or the number of people in your office? Those answers decide whether the tool saves time on the third job or only on the first.
Frequently asked questions
What is the best submittal software for steel contractors?
The best fit reads the Division 05 sections, lists every required submittal with its paragraph, and tracks each package through the GC, architect and engineer of record. Submittal does this and is priced per active project, from 24 USD a month billed yearly for one project, with reviewers free.
What submittals does a structural steel fabricator have to provide?
Typically erection and shop drawings, delegated connection calculations, mill test reports, bolt and anchor rod certificates, welding procedures, welder qualifications, fabricator certification and coating data. Joist, deck, stair and railing sections add their own drawings and calculations, and inspection reports close the job out.
Can I build a steel submittal log from the specifications?
Yes. Upload the project manual and Submittal creates one register row per item each Division 05 section requires, linked to its paragraph, including delegated design and certification items. You review the rows, set due dates from the erection schedule and group them into numbered packages.
Do steel subcontractors pay for the GC's submittal software?
It depends on the GC's platform. Many charge nothing to submit into it, but you still need your own list across jobs and GCs. A per project tool keeps that register in one place without paying a seat for every detailer and coordinator.
How much does submittal software cost for a steel company?
Submittal charges per active project, not per user. One project is 288 USD a year billed yearly, five projects 888 USD, and 25 projects 2,988 USD. The GC and reviewers you invite are unlimited.