| Submittal number | Section, sequence and revision, for example 087100-002-R1 | One number per package and revision, so nobody reviews a superseded set |
|---|
| Spec section | MasterFormat number and title, for example 08 71 00 Door Hardware | Ties the item to the scope a subcontractor bought |
|---|
| Paragraph | The article the requirement comes from, for example 1.4.B | Settles the argument about whether the spec asked for it |
|---|
| Type | Product data, shop drawings, samples, test reports, certificates, warranties, O&M data, mockups | Decides who reviews it and whether it needs a stamp |
|---|
| Category | Action, informational or closeout | Action items need approval before fabrication, informational items go on record, closeout items wait for turnover |
|---|
| Description | The requirement quoted from the spec | Lets the sub prepare the right documents the first time |
|---|
| Responsible | The company that prepares the package | Tells you who to chase |
|---|
| Reviewer route | GC reviewer, then architect, then consultant | Shows how many desks the package has to cross |
|---|
| Ball in court | Who holds the package today | The column everyone reads first |
|---|
| Date submitted | Date the package left the GC | Starts the review clock |
|---|
| Review due | Date submitted plus the contract review time | Shows when the architect owes an answer |
|---|
| Lead time | Fabrication and delivery time after approval | Feeds the submit-by date |
|---|
| Required on site | Date the material has to arrive | The date the schedule depends on |
|---|
| Submit by | Required on site minus lead time minus review time | The date the package has to leave the sub |
|---|
| Status and stamp | Not submitted, In review, Approved, Approved as noted, Revise and resubmit, Rejected, For record only | Tells you whether the order can be released |
|---|
| Returned | Date the stamp came back | Closes the cycle and shows real review time |
|---|