USACE submittal register software for ENG Form 4288 and UFGS specs

On a USACE, NAVFAC or Air Force job the submittal register is due with your QC plan, often within weeks of award, and the Government version rarely lists everything the specs require. Submittal reads the UFGS project specifications, lists every SD-01 to SD-11 item with its paragraph and its "G" approving authority, and shows you what the furnished register missed before your CQC manager signs it. You then run every transmittal, action code and resubmittal from one log and export it to Excel or PDF for the Contracting Officer.

Project coordinator taking a labeled binder from a shelf of submittal binders organized by spec division
1.0

Why the furnished register is not enough

UFGS 01 33 00 says it plainly: the register attached to the contract "may not be all-inclusive and additional submittals may be required." The Contractor has to verify that all required submittals are listed and add the missing ones before the register goes back with the QC plan and the schedule.

In practice that means one person, usually the CQC system manager or the project engineer, reads every technical section of a federal spec book and compares it line by line with a register that SpecsIntact exported at the end of design. Sections get edited after the export. Addenda add items. A "G" item listed under SD-07 Certificates deep in a mechanical section is easy to skip at 11 p.m., and a skipped "G" item turns into a rejected installation or a held pay item months later.

Submittal does the reading. You upload the project manual PDF, scanned or native, and it returns one row per required item, traced to the exact paragraph, with the SD number, the item description in the spec wording and the classification. Put it next to the Government register and the gaps are visible in minutes instead of days.

2.0

The columns UFGS 01 33 00 asks for, and where each one comes from

The Government fills some fields, the Contractor fills the rest, and the Contractor maintains the whole register for the life of the contract. Submittal keeps every one of those fields on each row.

Register fieldWho fills it under UFGS 01 33 00How Submittal handles it
Specification sectionGovernmentRead from the section number and title in the spec
SD number and type, for example SD-02 Shop DrawingsGovernmentRead from the submittal list in Part 1 of each section
Principal paragraphGovernmentLinked to the exact paragraph, one click opens the spec text
Classification, "G" plus reviewer code such as AE, DO, AO, RO or POGovernmentRead with the item, shown as the reviewer on the row
Activity numberContractorEntered once, kept in sync with your schedule export
Contractor submit, approval needed and material needed datesContractorBack-calculated from the material need date and lead time
Transmittal numberContractorConsecutive numbering in your format
Action code and datesContractor and approving authorityLogged on every return, with the revision history kept

Do not change the Government columns. Submittal flags any row it found in the spec that has no match in the furnished register, so you add items instead of rewriting what the Government delivered. The general guide to a submittal register covers the same columns on private work.

3.0

From UFGS spec book to a checked register

  • Upload the project manual PDF, including amended sections and addenda
  • Submittal finds every Division 01 to 48 section and reads the SD list in each Part 1
  • Each required item becomes a row with section, paragraph, SD number, description and "G" classification
  • Compare against the Government register and add the items it missed, in the same numbering
  • Enter activity numbers and need dates, and the submit dates back-calculate from lead times
  • Export the register to Excel, CSV or PDF for the Contracting Officer and keep it current every month

Reading the spec book automatically is explained in more depth on the construction specification software page.

4.1

The Contractor reviews first, then the Government

UFGS requires the Contractor's Quality Control organization to review and stamp every submittal, including those from subcontractors, before it goes to the Government. Items without a "G" are approved by the Contractor's QC system and sent for information only. Submittal mirrors that route: subcontractor upload, CQC review and stamp, then Government review for "G" items, with ball in court and reminders at each step.

4.2

Monthly updates without retyping

On design-build work the register is a scheduling document that is updated monthly with Contractor and Government action codes and actual dates. Because every transmittal and return is already logged, the monthly update is an export, not an afternoon of copying dates from email.

4.3

Subcontractors join at no cost

Your mechanical, electrical and fire protection subs upload their own packages through portal links on Team and higher plans. They never need a seat, and every revision lands on the right row. See how it works for trade partners on the subcontractor software page.

5.0

Prime contractors on federal construction

  • General contractors on USACE design-bid-build contracts who must verify and complete the Government register within the first weeks
  • Design-build teams who prepare the register themselves and submit it within 30 calendar days after Notice to Proceed
  • CQC system managers who carry several task orders at once on a MATOC or SATOC
  • Specialty contractors who need their own SD list from a federal spec book before they price or buy out
  • Small businesses winning their first federal job, without a document control department

If you are still looking for the next solicitation, a dedicated federal contract opportunity search helps you find and track bids before the register work starts.

6.0

Working alongside RMS CM and CMP

Many Army contracts require the Resident Management System contractor mode or the newer Construction Management Platform as the system of record, and your official transmittals go through it. Submittal does not replace that requirement. It is the working tool that builds and checks the register from the spec, keeps your subs' packages and CQC reviews in one place, and exports clean data you enter or upload into the Government system. On Navy and Air Force work, or on contracts that do not mandate RMS, the register you export from Submittal can serve as the register itself.

7.0

Priced per active project, no sales call

PlanYearly, per monthMonthlyActive projectsSpec pages per month
Starter24 USD (288 USD a year)49 USD11,500
Team74 USD (888 USD a year)149 USD58,000
Business249 USD (2,988 USD a year)499 USD2540,000
Enterprise749 USD (8,988 USD a year)1,499 USD100150,000

A typical federal project manual of 1,000 to 3,000 pages fits Team. US data residency, audit log and SSO are on the higher plans. The full comparison is on the submittal management software page, and security details are on the security page.

8.0

Frequently asked questions

What is a submittal register?

A submittal register is the list of every submittal the contract requires, one row per item, with the spec section, paragraph, submittal type, reviewer and the dates each item must be submitted, approved and delivered. On USACE contracts it is ENG Form 4288 and serves as the control document for submittals through closeout.

Who prepares the submittal register on a USACE project?

On design-bid-build work the Government furnishes the initial register from the specifications, and the Contractor verifies it, adds missing submittals and fills in activity numbers and dates. On Army design-build work the Contractor completes the register and submits it for approval within 30 calendar days after Notice to Proceed.

What does "G" mean on a submittal?

A "G" classification means the submittal requires Government approval. On Army projects a code after the G names the reviewing office, for example AE for the Architect-Engineer, DO for District Office or AO for Area Office. Items without a G or S classification are approved by the Contractor's quality control system and sent for information.

What are the SD numbers in UFGS specs?

SD numbers group submittals by type. They run from SD-01 Preconstruction Submittals, SD-02 Shop Drawings and SD-03 Product Data through SD-04 Samples, SD-05 Design Data, SD-06 Test Reports, SD-07 Certificates, SD-08 Manufacturer's Instructions, SD-09 Manufacturer's Field Reports, SD-10 Operation and Maintenance Data and SD-11 Closeout Submittals.

Can Submittal read SpecsIntact UFGS specifications?

Yes. UFGS sections published from SpecsIntact are PDF project manuals with standard section numbering and an SD list in Part 1, which is what Submittal reads. Scanned copies work too. Every row links back to the paragraph, so your CQC manager can check any item against the source.

Does it replace RMS or CMP?

No. When your contract makes RMS CM or CMP the system of record, official transmittals still go through it. Submittal builds and checks the register, runs reviews with your subs and exports the data you need for the Government system.